We are excited to share the key achievements of our construction project, made during 9 months:
- Concrete Poured: approx. 30 000 m3
- Rebars Installed: 4 000 tons
- Finished temporary facilities: 5 site offices, 7 worker canteens, 45 camp buildings, which accommodate approx. 500 people.
- Safety Milestones: Achieved over 1 000 000 man-hours without a lost-time incident.
- Workforce Impact: Created over 528 local jobs, supporting the community.




We would like to thank everyone involved for the hard work and dedication!