Syrdarya 2
Project Period:
Construction period: 2023 – 2026
Phase 2
Operating period: 2026-2051
Project Location:
Project Details
The construction phase of the project officially commenced in March 2023, with the Commercial Operating Date (COD) scheduled for June 2026. Upon completion, the plant will be fully operational, utilizing a combined cycle configuration comprising two gas turbines and one steam turbine. In order to ensure the successful delivery of the project, ENERSOK has appointed Harbin Electric International Company Limited as the Engineering, Procurement, and Construction (EPC) contractor. Harbin Electric is responsible for the comprehensive engineering design, procurement of all necessary equipment, and the construction of both temporary and permanent facilities. The selection of Harbin Electric was the result of a highly competitive tender process, in which five international EPC contractors were evaluated rigorously based on their financial stability, technical expertise, and environmental and social (E&S) qualifications. This rigorous selection process ensures that the project is executed with the highest levels of quality, efficiency, and sustainability, as well full compliance with international standards of IFC.
Main facilities:
Power block and stacks including two Gas Turbines (GT), two Heat Recovery Steam Generators (HRSG) and one Steam Turbine (ST)
Closed Loop Cooling Water system, with mechanical draft air cooling tower blocks
Gas receiving terminal
Access road
Intake and outfall corridor to a surface water canal, known as the YG Canal
Wastewater treatment plants (industrial and sanitary)
Ancillary facilities
500/220kv switchgear station shared with and being constructed by the adjacent ACWA Power Syrdarya 1,500MW CCGT Power Plant
Associated Facilities:

1 km gas pipeline connection to an existing gas supply system and operated by the gas supplier, JSC Uztransgaz.
Re-routing of an existing 500kV Overhead Transmission Line (OHTL) by NEGU.